2F North Gate Center, Gov. Cuenco Ave.,
Banilad, Cebu City, Philippines
Phone : (032) 418-1088

Projects


Roads

CLUSTER “A” REHABILITATION/MAJOR REPAIR OF VARIOUS PERMNRIDGES (Roads)-

  • Location: Bukidnon
  • Owner: DPWH Region X
  • Cost: 11.6M
  • Period: 80 C.D.
  • Status: Completed / November 2017

IMPROVEMENT/WIDENING OF FATIMA-MALABOG
ROAD INCLUDING SLOPE PROTECTION DAVAO CITY (ROADS)

  • Location: Davao City
  • Owner: DPWH – Davao City District Engineering Office
  • Cost: 22.7M
  • Period: 164 C.D.
  • Status: Completed / October 2017

CONCRETING OF BRGY.LUKAY – BRGY.MALAGUINABOT – BRGY. CABATIANUHAN FMR (ROADS)

  • Location: SAN MIGUEL, LEYTE
  • Owner: DPWH – Leyte 1st District Engineering Office
  • Cost: 4.7M
  • Period: 61 C.D.
  • Status: Completed / September 2017

OFF-CARRIAGEWAY IMPROVEMENT INCLUDING DRAINAGE OF DAVAO CITY DIVERSION ROAD (ROADS)

  • Location: Davao City
  • Owner: DPWH – Davao City District Engineering Office
  • Cost: 38.4M
  • Period: 132 C.D.
  • Status: Completed / September 2017

CONSTRUCTION: ROAD IMPROVEMENT JCT TURNO BY PASS ROAD TO LINABO PEAK (3,003 STEPS) (ROADS)

  • Location: Dipolog City
  • Owner: DPWH – Zamboanga del Norte 1st District Engineering Office
  • Cost: 22.3M
  • Period: 148 C.D.
  • Status: Completed / August 2013

REHABILITATION: ROAD IMPROVEMENT JCT. BRGY. COGON HIGHWAY TO SUNGKILAW FALLS (ROADS)

  • Location: Zamboanga Del Norte
  • Owner: DPWH – Zamboanga del Norte 1st District Engineering Office
  • Cost: 23.4M
  • Period: 102 C.D.
  • Status: Completed / June 2013

TRAFFIC ENGINEERING- PAVEMENT MARKINGS: PREVENTIVE MAINTENANCE ALONG SINDANGAN-SIAYANDUMINGAG ROAD PIAOBUYOS SECTION (ROADS)

  • Location: Zamboanga Del Norte
  • Owner: DPWH – Zamboanga del Norte 1st District Engineering Office
  • Cost: 649K
  • Period: 33 C.D.
  • Status: Completed / March 2013

REHABILITATION-ASPHALT: PREVENTIVE MAINTENANCE ALONG SINDANGAN-SIAYANDUMINGAG ROAD PIAOBUYOS SECTION (ROADS)

  • Location: Zamboanga Del Norte
  • Owner: DPWH – Zamboanga del Norte 1st District Engineering Office
  • Cost: 9.0M
  • Period: 33 C.D.
  • Status: Completed / March 2013

WIDENING OF AKLAN EAST ROAD, KALIBO, AKLAN (ROADS)

  • Location: Zamboanga Del Norte
  • Owner: DPWH- Aklan District Engineering Office
  • Cost: 43.9M
  • Period: 171 C.D.
  • Status: Completed / July 2013

UPGRADING/REHABILITATION INCLUDING SLOPE PROTECTION OF CATICLAN – KALIBO (AKLAN WEST ROAD), AKLAN (ROADS)

  • Location: Aklan
  • Owner: DPWH- Region VI
  • Cost: 90.3M
  • Period: 269 C.D.
  • Status: Completed / October 2013

REHABILITATION:  CONSTRUCTION/IMPROVEMENT OF BORACAY CIRCUMFERENTIAL ROAD, BORACAY ISLAND, MALAY, AKLAN (ROADS)

  • Location: Aklan
  • Owner: DPWH- Aklan District Engineering Office
  • Cost: 29.9M
  • Period: 129 C.D.
  • Status: Completed / May 2013

CONSTRUCTION: CONSTRUCTION/IMPROVEMENT OF BORACAY CIRCUMFERENTIAL ROAD, MALAY, AKLAN, SEC. I: STA. 000+000 – STA. 001+080; SEC (ROADS)

  • Location: Boracay
  • Owner: DPWH- Region VI
  • Cost: 44.3M
  • Period: 211 C.D.
  • Status: Completed / February 2013

REPAIR OF LANGKILAAN ROAD DEPRESSION/SETTLEMENT DAANG MAHARLIKA ROAD (AGUSAN-DAVAO SECTION) (ROADS)

  • Location: Agusan del Sul
  • Owner: DPWH-Agusan del Sur 2nd District Engineering Office
  • Cost: 9.4M
  • Period: 286 C.D.
  • Status: Completed / March 2013

IMPROVEMENT OF JNH BAUK-BAUK-KABANGASAN-MAPUA RD IN KAMADA-ARC BALINGOAN, MISAMIS ORIENTAL (ROADS)

  • Location: Misamis Oriental
  • Owner: DPWH- Misamis Oriental 1st District Engineering Office
  • Cost: 35.8M
  • Period: 301 C.D.
  • Status: Completed / January 2013

CONSTRUCTION OF LUGUSAN BRIDGE AND APPROACHES ALONG SURIGAO DEL SUR BOUNDARY, DAVAO ORIENTAL COASTAL ROAD (ROADS)

  • Location: Davao Oriental
  • Owner: DPWH- Region XI
  • Cost: 13.9M
  • Period: 256 C.D.
  • Status: Completed / January 2013

REPAIR/REHABILITATION & CONSTRACTION OF FMR, MANIKA-SITIO TAROYTOY FMR, MANIKA, LIBACAO, AKLAN (ROADS)

  • Location: Aklan
  • Owner: DPWH – Aklan District Engineering Office
  • Cost: 13.7M
  • Period: 211 C.D.
  • Status: Completed / November 2012

IMPROVEMENT/CONCLUSION OF SOCORRO-NUEVA ESTRELLA-PAMOSAINGAN RD., SOCORRO, SURIGAO DEL NORTE (ROADS)

  • Location: Misamis Oriental
  • Owner: DPWH- Surigao del Norte 2nd District Engineering Office
  • Cost: 35.8M
  • Period: 301 C.D.
  • Status: Completed / September 2012

REHABILITATION/RECONSTRUCTION/UPGRADNG OF DAMAGED PAVED NATIONAL ROAD GEN FR PMS/HDM-4 (INTERMITTENT SECTION) SH K1594+000-1596 (ROADS)

  • Location: Boracay
  • Owner: DPWH- Region X
  • Cost: 22.5M
  • Period: 211 C.D.
  • Status: Completed / September 2012

CONSTRUCTION/IMPROVEMENT/CONCRETING OF TOMOAONG BRIDGE APPROACHES ALONG SURIGAO DEL SUR BOUNDARY DAVAO ORIENTAL COASTAL ROAD (ROADS)

  • Location: SURIGAO DEL SUR
  • Owner: DPWH- Region XI
  • Cost: 22.7M
  • Period: 113 C.D.
  • Status: Completed / August 2012

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROAD GEN. FROM PAVEMENT MGT. HDM4 DIPOLOG-OROQUIETA (ROADS)

  • Location: Zamboanga del Norte
  • Owner: DPWH- Zamboanga del Norte
  • Cost: 11.3M
  • Period: 35 C.D.
  • Status: Completed / August 2012

REPAIR/REHABILITATION/IMPROVEMENT OF ROMAN EXPRESSWAY, LIMAY, BATAAN (ROADS)

  • Location: Limay, Bataan
  • Owner: DPWH – Bataan 2nd District Engineering Office
  • Cost: 540K
  • Period: 11 C.D.
  • Status: Completed / July 2012

CONSTRUCTION/IMPROVEMENT/CONCRETING OF TOMOAONG BRIDGE APPROACHES ALONG SURIGAO DEL SUR BOUNDARY- DAVAO ORIENTAL (ROADS)

  • Location: Davao Oriental
  • Owner: DPWH- Region XI
  • Cost: 22.7M
  • Period: 113 C.D.
  • Status: Completed / August 2012

REPAIR/REHABILITATION/IMPROVEMENT OF JCT. LAYAC-BALANGA – MARIVELES PORT ROAD, LIMAY, BATAAN (ROADS)

  • Location: Limay, Bataan
  • Owner: DPWH – Bataan 2nd District Engineering Office
  • Cost: 512K
  • Period: 9 C.D.
  • Status: Completed / June 2012

COMPLETION(CONCRETING) OFBORACAY CIRCUMFERENTIAL ROAD, K001+600 – K002+400, BOLABOG-TULUBHAN, AKLAN (ROADS)

  • Location: Aklan
  • Owner: DPWH – Region VI
  • Cost: 18.9M
  • Period: 121 C.D.
  • Status: Completed / May 2012

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROAD GENERATED FROM MANAGEMENT SYSTEM/HIGHWAY DEVELOPMENT (ROADS)

  • Location: Zamboanga del Norte
  • Owner: Zamboanga del Norte 1st District Engineering Office
  • Cost: 21.6M
  • Period: 61 C.D.
  • Status: Completed / April 2012

REHABILITATION/CONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROAD GENERATED FROM PAVEMENT MANAGEMENT SYSTEM (ROADS)

  • Location: Zamboanga del Norte
  • Owner: Zamboanga del Norte 1st District Engineering Office
  • Cost: 8.4M
  • Period: 119 C.D.
  • Status: Completed / April 2012

PREVENTIVE MAINTENANCE (ASPHALT OVERLAY/INSTAPAVE SURFACE TREAMENT) (ROADS)

  • Location: Zamboanga del Norte
  • Owner: Zamboanga del Norte 1st District Engineering Office
  • Cost: 9.5M
  • Period: 51 C.D.
  • Status: Completed / April 2012

PREVENTIVE MAINTENANCE (INTERMITTENTSECTION) – DIPOLOG- SINDANGAN-LILOYROAD (ROADS)

  • Location: Zamboanga del Norte
  • Owner: Zamboanga del Norte 1st District Engineering Office
  • Cost: 16.04M
  • Period: 89C.D.
  • Status: Completed / March 2012

INDIVIDUAL PROJECT-CONCRETING OF SAN ROQUE-OMBAO POLPOGFMR, BULA, CAMARINES SUR (ROADS)

  • Location: Camarines Sur
  • Owner: DPWH- Camarines Sur 4th District Engineering Office
  • Cost: 9.5M
  • Period: 66 C.D.
  • Status: Completed / March 2012

REHAB/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROAD HDM4 (ROADS)

  • Location: Zamboanga del Norte
  • Owner: DPWH- Zamboanga del Norte 1st District
  • Cost: 17.2M
  • Period: 91 C.D.
  • Status: Completed / March 2012

REPAIR/REHAB/IMPR’VT.OF ROMAN EXPRESSWAY,  LIMAY, BATAANKM. 135+410-KM. 137+500 W/EXCEPTION (ROADS)

  • Location: Bataan
  • Owner: DPWH- Bataan 2nd District Engineering Office
  • Cost: 9.4M
  • Period: 20 C.D.
  • Status: Completed / February 2012

PREVENTIVE MAINTENANCE (INTERMITTENT SECTION) (ROADS)

  • Location: Bataan
  • Owner: DPWH- Zamboanga del Norte 1st District Engineering Office
  • Cost: 5.3M
  • Period: 61 C.D.
  • Status: Completed / February 2012

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED ROAD (ROADS)

  • Location: Zamboanga del Norte
  • Owner: DPWH- Zamboanga del Norte 1st District
  • Cost: 6.3M
  • Period: 59 C.D.
  • Status: Completed / February 2012

REPAIR/REHABILITATION/IMPROVEMENT OF JCT. LAYAC-BALANGA- MARIVELES, LIMAY, BATAAN KM.140+000-KM.141+000 W/EXCEPTION (ROADS)

  • Location: Bataan
  • Owner: DPWH- Bataan 2nd District Engineering Office
  • Cost: 9.4M
  • Period:  16 C.D.
  • Status: Completed / February 2012

CONSTRUCTION/WIDENING OF JACINTO BORJA BRIDGE AND WIDENING OF CAUSEWAY JCT. T.E.R. DAUIS-PANGLAO ROAD (ROADS)

  • Location: Panglao
  • Owner: DPWH- Region VII
  • Cost: 38.6M
  • Period:  1887 C.D.
  • Status: Completed / January 2012

RECONSTRUCTION OF CRITICAL SECTION ALONG NATIONAL ROAD,ROAD SLIP ALONG DIPOLOG-SERGIO OSMEÑA ROAD SANGKOL (ROADS)

  • Location: Zamboanga del Norte
  • Owner: DPWH- Zamboanga del Norte 1st District Engineering Office
  • Cost: 17.4M
  • Period:  112 C.D.
  • Status: Completed / December 2011

CP-4: IMPROVEMENT/CONCLUSION OF KAPALONG-TALAINGOD-
VALENCIA, BUKIDNON ROAD, BRGY. STO.NINO
SECTION, PHASE I (ROADS)

  • Location: Bukidnon
  • Owner: DPWH- Region XI
  • Cost: 139.5M
  • Period:  1153 C.D.
  • Status: Completed / August 2011

CP-8 CONSTRUCTION OF SIX(6) BRIDGES INCLUDING ALONG KAPALONG-TALAINGOD-VALENCIA, BUKIDNON RD. (ROADS)

  • Location: Zamboanga del Norte
  • Owner: DPWH- Region XI
  • Cost: 38.0M
  • Period:  1020 C.D.
  • Status: Completed / April 2011

REPAIR/ASPHALT OVERLAY ALONG DIPOLOG-OROQUIETA NATIONAL ROAD STA. 1844+200 TO KM. 1847+500 (ROADS)

  • Location: Zamboanga del Norte
  • Owner: DPWH- Zamboanga del Norte 1st District Engineering Office
  • Cost: 38.0M
  • Period:  126 C.D.
  • Status: Completed / February 2011

UPGRADING/IMPROVMENT ALONG SINDANGAN- SIAYAN-DUMINGAGROAPIAO-SIAYANSECTION, ZAMBO.DEL NORTE (ROADS)

  • Location: Zamboanga del Norte
  • Owner: DPWH- Zamboanga del Norte 1st District Engineering Office
  • Cost: 18.6m
  • Period:  94C.D.
  • Status: Completed / January 2011

REPAIR/MAINTENANCE OF NATIONAL ROADS & BRIDGES (REPAIR/MAINTENANCE OF DAMAGED PAVEMENT) (ROADS)

  • Location: Zamboanga del Norte
  • Owner: DPWH- Zamboanga del Norte 1st District Engineering Office
  • Cost: 2.7M
  • Period:  59 C.D.
  • Status: Completed / December 2010

IMPRVOVEMENT/REHABILITATION (ASPHALT OVERLAY) ALONG CNHWR KM24+250 TOKM27+000 COMPOSTELA SECTION W/ EXCEPTION (ROADS)

  • Location: Compostela
  • Owner: DPWH- Cebu 5th District Engineering Office
  • Cost: 19.6M
  • Period:  35 C.D.
  • Status: Completed / August 2010

UPGRADING/IMPROVEMENT OF VARIOUS FMR (TORRIJOS MARINDUQUE) (ROADS)

  • Location: Marinduque
  • Owner: DPWH- Marinduque District Engineering Office
  • Cost: 9.6M
  • Period: 101 C.D.
  • Status: Completed / September 2010

UPGRADING/IMPROVEMENT OF VARIOUS FMR (BUENAVISTA, MARINDUQUE) (ROADS)

  • Location: Marinduque
  • Owner: DPWH – Marinduque District Engineering Office
  • Cost: 7.6M
  • Period: 91 C.D.
  • Status: Completed / September 2010

IMPROVEMENT/REHABILITATION (ASPHALT OVERLAY) ALONG SOGOD TABUELAN ROAD KM 118+000 TO KM121+000 W/EXCEPTIONS (ROADS)

  • Location: Tabuelan, Cebu
  • Owner: DPWH- Cebu 5th District Engineering Office
  • Cost: 19.7M
  • Period: 28 C.D.
  • Status: Completed / August 2010

PREVENTIVE MAINTENANCE OF DIPOLOG-SINDANGAN- LILOY ROAD (ROADS)

  • Location: Tabuelan, Cebu
  • Owner: DPWH- Zamboanga del Norte 1st District Engineering Office
  • Cost: 4.8M
  • Period: 8 C.D.
  • Status: Completed / June 2010

ROAD TO COMPLETE NAUTICAL HIGHWAY, REHABILITATION OF DAANG MAHARLIKA, SOUTHERN LEYTE (ROADS)

  • Location: Southern Leyte
  • Owner: DPWH- Southern Leyte District Engineering Office
  • Cost: 34.6M
  • Period: 366 C.D.
  • Status: Completed / March 2010

UPGRADING OF BARANDIAS-DOMINOROG ROAD, BACUSANON SECTION, BUKIDNON (ROADS)

  • Location: BUKIDNON
  • Owner: DPWH – Region X
  • Cost: 27.6M
  • Period: 211 C.D.
  • Status: Completed / January 2010

IMPROVEMENT OF CATIGBIAN-MACAAS ROAD TUBIGON BOHOL (ROADS)

  • Location: Bohol
  • Owner: DPWH – Region VII
  • Cost: 57.9M
  • Period: 266 C.D.
  • Status: Completed / December 2009

CP-5: IMPROVEMENT/CONCLUSION OF KAPALONG-TALAINGOD VALENCIA,
BUKIDNON RD. BRGY. STO NINO SECT, PHASE-2 DAVAO (ROADS)

  • Location: Davao
  • Owner: DPWH – Region XI
  • Cost: 22.7M
  • Period:550 C.D.
  • Status: Completed / December 2009

REHABILITATION/RECONSTRUCTION OF CNHWR(INTERMITTENT SECT.) KM.14+505-KM.21+815, KM. 27+169-KM. 38+044, KM. (ROADS)

  • Location: Cebu
  • Owner: DPWH- Cebu 5th District Engineering Office
  • Cost: 99.5M
  • Period: 498C.D.
  • Status: Completed / November 2009

TRAFFIC ENGINEERING-PAVEMENT MARKINGS: REHABILITATION/RECONSTRUCTION OF CNHWR(INTERMITTENT SECT.) KM.14+505-KM.21+815, KM. 27+169-KM. 38+044, KM. (ROADS)

  • Location: Cebu
  • Owner: DPWH- Cebu 5th District Engineering Office
  • Cost: 6.1M
  • Period: 498C.D.
  • Status: Completed / November 2009

REHABILITATION/RECONSTRUCTION/UPGRADING OF DAMAGED PAVED NATIONAL ROADS
GENERATED FROM PAVEMENTMANAGEMENT (ROADS)

  • Location: Aklan
  • Owner: DPWH- Aklan District Engineering Office
  • Cost: 31.7M
  • Period: 222C.D.
  • Status: Completed / October 2009

IMPROVEMENT OF JCT. (TNR) CORTES BALILIHAN- CATIGBIAN ROAD BALILIHAN CORTES SECTION (ROADS)

  • Location: Catigbian
  • Owner: DPWH- Region VII
  • Cost: 65.5M
  • Period: 211 C.D.
  • Status: Completed / October 2009

CLUSTER I-A.) CONCRETING OF ROADS AT BRGY BASAK COMPOSTELA CEBU, B.) BRGY BAGAINGA, C.) BRGY COGON (ROADS)

  • Location: Cebu
  • Owner: DPWH- Cebu 5th District Engineering Office
  • Cost: 8.0M
  • Period: 71 C.D.
  • Status: Completed / August 2009

Cluster – Concreting of Roads, Compostela and Carmen, Cebu (Roads)

  • Location: Compostela / Carmen, Cebu
  • Owner: DPWH Cebu 5th Engg District
  • Cost: 10.1M
  • Period: 90 C.D.
  • Status: Completed / June 2009

Rehab. / Reconst. Of Damaged Paved National Road (Roads)

  • Location: Altavas, Aklan
  • Owner: DPWH Kalibo Engg District
  • Cost: 19.2M
  • Period: 270 C.D.
  • Status: Completed / December 2008

Concreting of Bais-Kabankalan Road Intermittent Section (Roads)

  • Location: Province of Negros Oriental
  • Owner: DPWH Region VII
  • Cost: 95.2M
  • Period: 300 C.D.
  • Status: Completed / July 2008

Concreting of Altavas Diversion Roads, Altavas, Aklan (Roads)

  • Location: Altavas, Aklan
  • Owner: DPWH Region VI
  • Cost: 16.5M
  • Period: 120 C.D.
  • Status: Completed / January 2008

Maintenance / Rehab. / Improvement of Toledo-Aloguinsan Mantalongon Road Km. 81,900-84,400 (Roads )

  • Location: Aloguinsan, Cebu
  • Owner: DPWH Region VII
  • Cost: 14.9M
  • Period: 28 C.D.
  • Status: Completed / September 2007

Maintenance / Rehab. / Improvement of Toledo-Aloguinsan Mantalongon Road Km. 79,400-80,900 (Roads)

  • Location: Aloguinsan, Cebu
  • Owner: DPWH Region VII
  • Cost: 14.9M
  • Period: 28 C.D.
  • Status: Completed / September 2007

Repair / Rehab. Of Mactan Circumferencial Road (Pusok-Ibo-Buaya Section) Lapu-Lapu City (Roads)

  • Location: Lapu – lapu City
  • Owner: DPWH Region VII
  • Cost: 18.2M
  • Period: 40 C.D.
  • Status: Completed / November 2006

Canduman Upscaling & Empowerment Project (Roads)

  • Location: Canduman, Mandaue City
  • Owner: Roman Aboitiz Foundation
  • Cost: 11.4M
  • Period: 105 C.D.
  • Status: Completed / April 2005

Rehabilitation of Mandagao-Nueva Era Farm to Market Road (Roads)

  • Location: Bunawan, Agusan Sur
  • Owner: LGU City of Bunuwan
  • Cost: 10.3M
  • Period: 180 C.D.
  • Status: Completed / July 2003

Concreting of Cortes-Balilihan Catigbian National Road, Province of Bohol (Roads)

  • Location: Cortes, Bohol
  • Owner: DPWH Regional Office
  • Cost: 48M
  • Period: 470 C.D.
  • Status: Completed / November 2003

Improvement of Loay Interior Road, Province of Bohol (Roads)

  • Location: Carmen, Bohol
  • Owner: DPWH Bohol 2nd Engg District
  • Cost: 22.1M
  • Period: 240 C.D.
  • Status: Completed / August 2003

Construction of Corella to Sikatuna Road, Province of Bohol (Roads)

  • Location: Corella/Sikatuna, Bohol
  • Owner: DPWH Bohol 1st Engg District
  • Cost: 13.9M
  • Period: 300 C.D.
  • Status: Completed / November 2002

Const. of Loay Interior Road, San Miguel-Dagohoy Section (Roads)

  • Location: Bohol Province
  • Owner: DPWH Region VII
  • Cost: 14.8M
  • Period: 150 C.D.
  • Status: Completed / December 2002

Concreting of JCT Nat. Road Cuartero-Maindang-Tapulang-Maayon Road, Cueartero Sectoion, Capiz (Roads)

  • Location: Capiz
  • Owner: DPWH Capiz Engineering District
  • Cost: 18M
  • Period: 300 C.D.
  • Status: Completed / May 2002

Rehab. / Concreting of Dumiog Cambang-ug-Malubog Brgy. Road (Roads)

  • Location: Toledo City
  • Owner: DPWH Region VII
  • Cost: 28M
  • Period: 300 C.D.
  • Status: Completed / July 2001

Asphalting / Widening of g. Ouna St., Mandaue City (Roads)

  • Location: Mandaue City
  • Owner: LGU City of Mandaue
  • Cost: 56M
  • Period: 360 C.D.
  • Status: Completed / January 2000

Ports

CONSTRUCTION/WIDENING OF JACINTO BORJA BRIDGE AND WIDENING OF
CAUSEWAY JCT. T.E.R. DAUIS-PANGLAO ROAD (Port)

  • Location: Bohol
  • Owner: DPWH – Region VII
  • Cost: 19.2M
  • Period: 1887 C.D.
  • Status: Completed / January 2012

Extension of R.C. Pier and Const. Roro Ramp at Brgy. Balite, Kawayan, Biliran Province (Port)

  • Location: Kawayan, Biliran Province
  • Owner: Phil. Port Authority
  • Cost: 13.9M
  • Period: 110 C.D.
  • Status: Completed / March 2008

Improvement of Padre Burgos Port, Padre Burgos, Southern Leyte (Port)

  • Location: Padre Burgos, So. Leyte
  • Owner: Phil. Port Authority
  • Cost: 11.8M
  • Period: 115 C.D.
  • Status: Completed / December 2007

Provision of R.C. Deck with Roro Ramp at Port of Sta. Rosa (Port)

  • Location: Sta. Rosa, Lingo Is.
  • Owner: Cebu Port Authority
  • Cost: 12.3.M
  • Period: 180 C.D.
  • Status: Completed / January 2005

Repair / Rehab. / Improvement of Lazi Wharf (Dredging Works) (Port)

  • Location: Lazi, Siquijor
  • Owner: Province of Lazi, Siquijor
  • Cost: 45.1M
  • Period: 300 C.D.
  • Status: Completed / April 2003

Reclamation of Pulang Bato Port (Port)

  • Location: Bogo, Cebu
  • Owner: Rainbow Ferry Inc.
  • Cost: 17M
  • Period: 130 C.D.
  • Status: Completed / December 1996

Buildings

CONSTRUCTION OF BRGY. HEALTH STATION-BIRTHING FACILITY T DAMILAG PAQUIBATO DISTRICT, DAVAO CITY (Building)

  • Location: Davao City
  • Owner: DPWH – Davao City District Engineering Office
  • Cost: 1.9M
  • Period: 61 C.D.
  • Status: Completed / July 2017

CONSTRUCTION OF 4 STOREY 20 CLASSROOM SCHOOL BUILDING AT CAMOTES NATIONAL HIGH SCHOOL, SAN FRANCISCO, CEBU (Building)

  • Location: Cebu
  • Owner: DPWH – Cebu 5th District Engineering Office
  • Cost: 31.7M
  • Period: 231 C.D.
  • Status: Completed / June 2017

CONSTRUCTION OF 2 UNITS – 4 STOREY, 20 CLASSROOM SCHOOL BUILDING AT ARCELO MNHS, LILOAN, CEBU (Building)

  • Location: Cebu
  • Owner: DPWH – Cebu 5th District Engineering Office
  • Cost: 59.5M
  • Period: 231 C.D.
  • Status: Completed / April 2017

CONSTRUCTION OF 4 STOREY 8 – CLASSROOM SCHOOL BUILDING AT ARCELO MNHS, LILOAN, CEBU(Building)

  • Location: Cebu
  • Owner: DPWH – Cebu 5th District Engineering Office
  • Cost: 14.1M
  • Period: 181 C.D.
  • Status: Completed / March 2017

CONSTRUCTION OF MULTIPURPOSE BUILDING (WATCHLIFE WORKERS), MARIVELES, BATAAN(Building)

  • Location: Cebu
  • Owner: DPWH – Cebu 5th District Engineering Office
  • Cost: 290k
  • Period: 25 C.D.
  • Status: Completed / April 2011

CLUSTER I-A) CONCRETING OF ROADS AT BRGY BASAK COMPOSTELA CEBU, B) BRGY BAGAINGA, C)BRGY. COGON(Building)

  • Location: Cebu
  • Owner: DPWH – Cebu 5th District Engineering Office
  • Cost: 2.1M
  • Period: 70 C.D.
  • Status: Completed / August 2009

Construction of Hall of Justice Lawaan 2, Talisay City (Building)

  • Location: Lawaan 2, Talisay City
  • Owner: City of Talisay
  • Cost: 24.9M
  • Period: 180 C.D.
  • Status: Completed / July 2006

Construction of Pension House (Building)

  • Location: Maria, Siquijor
  • Owner: Province of Siquijor
  • Cost: 9.4M
  • Period: 200 C.D.
  • Status: Completed / June 2005

Conversion of Exisiting Transit Shed to Passenger Terminal at Pier 1 (Building)

  • Location: Pier 1, Port of Cebu
  • Owner: Cebu Port Authority
  • Cost: 12.4M
  • Period: 150 C.D.
  • Status: Completed / March 2004

Construction of Glaxonsmithkline Philippines, Inc. / E-Call Business Building (Building)

  • Location: Makati City
  • Owner: Gloxosmithkline Phil. Inc.
  • Cost: 9.8M
  • Period: 130 C.D.
  • Status: Completed / September 2003

Construction of Maghaway Detention & Rehab. Center (Building)

  • Location: Talisay City
  • Owner: City of Talisay
  • Cost: 15.5M
  • Period: 180 C.D.
  • Status: Completed / November 2002

Construction of Shell Gas Station (Building)

  • Location: Jaro, Ilo-ilo City
  • Owner: Pilipinas Shell
  • Cost: 9.8M
  • Period: 150 C.D.
  • Status: Completed / January 1998

Site Development of Villa Romana (Site Development)

  • Location: Bohol
  • Owner: Mr. Balili
  • Cost: 107M
  • Period: 360 C.D.
  • Status: Completed / October 1997

Construction of 5 Storey Post Tensioning Building (Building)

  • Location: Ilo-ilo City
  • Owner: Mr. Saturino
  • Cost: 15M
  • Period: 130 C.D.
  • Status: Completed / January 1997

Construction of 18 Storey Park Tower 1 (Building)

  • Location: Ayala, Cebu
  • Owner: Sub-Contract
  • Cost: 16M
  • Period: 130 C.D.
  • Status: Completed / December 1996

Construction of San Remegio Sports Complex (Building)

  • Location: San Remegio, Cebu
  • Owner: Municapal Govt of San Remegio
  • Cost: 9.4M
  • Period: 120 C.D.
  • Status: Completed / December 1996

Rehabilitation of Verallo Hospital (Building)

  • Location: Bogo, Cebu
  • Owner: Dept. of Health
  • Cost: 18M
  • Period: 180 C.D.
  • Status: Completed / December 1995

Construction of Daan Bantayan Sports Complex (Building)

  • Location: Daan Bantayan, Cebu
  • Owner: Municipal Govt of Daan Bantayan
  • Cost: 11.4M
  • Period: 120 C.D.
  • Status: Completed / November 1995

Construction of Public Stage (Building)

  • Location: Daan Bantayan, Cebu
  • Owner: Municipal Govt of Daan Bantayan
  • Cost: .75M
  • Period: 30 C.D.
  • Status: Completed / October 1995

Construction of Residential Building (Building)

  • Location: Bogo, Cebu
  • Owner: Dana Nilda Martinez
  • Cost: 12M
  • Period: 150 C.D.
  • Status: Completed / October 1995

Construction of Sta. Fe Municipal Building (Building)

  • Location: Sta. Fe, Cebu
  • Owner: Municipal Govt of Sta. Fe
  • Cost: 14M
  • Period: 180 C.D.
  • Status: Completed / September 1995

Bridges

CLUSTER “A” REHAB./MAJOR REPAIR OF VARIOUS PERMNRIDGES IN BUKIDNON (Bridge)

  • Location: Bukidnon
  • Owner: DPWH – Region X
  • Cost: 11.6M
  • Period: 80 C.D.
  • Status: Completed / November 2017

LOCALLY FUNDED PROJECTS – CONSTRUCTION/REPAIR/ REHABILITATION OF
VARIOUS INFRASTRUCTURE INCLUDING LOCAL PROJECTS ROADS AND BRIDGES LOCAL BRIDGES CONSTRUCTION OF 2 -LANE PRE-STRESSED CONCRETE GIRDER BRIDGE INCL. PIER AND SOIL EROSION MITIGATION
PROTECTION, UP LOS BAÑOS, LAGUNA (Bridge)

  • Location: Laguna
  • Owner: DPWH – Region IV-A
  • Cost: 62.3M
  • Period: 241 C.D.
  • Status: Completed / January 2017

CONSTRUCTION OF LUGUSAN BRIDGE AND APPROACHES ALONG SURIGAO DEL SUR BOUNDARY, DAVAO ORIENTAL COASTAL ROAD (Bridge)

  • Location: Davao Oriental
  • Owner: DPWH- Region XI
  • Cost: 13.7M
  • Period: 256 C.D.
  • Status: Completed / January 2013

CONSTRUCTION/WIDENING OF JACINTO BORJA BRIDGE AND WIDENING OF CAUSEWAY JCT. T.E.R. DAUIS-PANGLAO ROAD (Bridge)

  • Location: Panglao
  • Owner: DPWH- Region VII
  • Cost: 38.7M
  • Period:  1887 C.D.
  • Status: Completed / January 2012

CP-8 CONSTRUCTION OF SIX(6) BRIDGES INCLUDING ALONG KAPALONG-TALAINGOD-VALENCIA, BUKIDNON RD. (Bridge)

  • Location: Zamboanga del Norte
  • Owner: DPWH- Region XI
  • Cost: 66.4M
  • Period:  1020 C.D.
  • Status: Completed / April 2011

REPAIR OF OPOL BRIDGE APPROACHES & RECONSTRUCTION OF THE RIVER FLOOD CONTROL REVETMENT ALONG BUTUAN-CDOC-I (Bridge)

  • Location: Butuan
  • Owner: DPWH – Region X
  • Cost: 4.5M
  • Period: 181 C.D.
  • Status: Completed / September 2010

ROAD TO COMPLETE NAUTICAL HIGHWAY, REHABILITATION OF DAANG MAHARLIKA, SOUTHERN LEYTE (Bridge)

  • Location: Southern Leyte
  • Owner: DPWH- Southern Leyte District Engineering Office
  • Cost: 12.8M
  • Period: 366 C.D.
  • Status: Completed / March 2010

REPAIR/REHABILITATION OF CARAGA, QUINONOAN AND GOVERNOR LOPEZ BRIDGES ALONG DAVAO ORIENTAL-SURIGAO COASTAL RD (Bridge)

  • Location: Davao Oriental
  • Owner: DPWH- Region XI
  • Cost: 53.7M
  • Period: 394 C.D.
  • Status: Completed / January 2010

Construction of Banica Bridge Roxas City, Capiz (Bridge)

  • Location: Roxas City, Capiz
  • Owner: DPWH Region VI
  • Cost: 13.9M
  • Period: 270 C.D.
  • Status: Completed / February 2007

Construction of Mumaiag Bridge Poblacion-Dumalag-San Roque (Bridge)

  • Location: Dumalag, Capiz
  • Owner: DPWH Capiz 2nd Engg District
  • Cost: 14.9M
  • Period: 280 C.D.
  • Status: Completed / April 2006

Post-Tensioning of Girder Jaluar Bridge (Bridge)

  • Location: Ilo-ilo City
  • Owner: DPWH
  • Cost: 30M
  • Period: 200 C.D.
  • Status: Completed / August 1996

Fabrication of Pre-Street R.C. Piles-Kulipapa Bridge (Bridge)

  • Location: Ilo-ilo City
  • Owner: DPWH
  • Cost: 10M
  • Period: 150 C.D.
  • Status: Completed / July 1996

Construction of Anoling Bridge (Bridge)

  • Location: Ilo-ilo
  • Owner: RRDP
  • Cost: 11.8M
  • Period: 150 C.D.
  • Status: Completed / April 1996

Water System

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VIILP – WATER SUPPLY AND SANITATION FOR POVERTY AREAS AND TOURISM PRIORITY SITES, CONSTRUCTION OF VARIOUS WATER SUPPLY PROJECTS, GETAFE, BOHOL (WATER SYSTEM)

  • Location: Bohol
  • Owner: DPWH – Bohol 2nd District
  • Cost: 31.3M
  • Period: 181 C.D.
  • Status: Completed / July 2017

CONSTRUCTION/REPAIR/REHABILITATION/IMPROVEMENT OF VIILP- WATER SUPPLY
AND SANITATION OF POVERTY AREAS AND TOURISM PRIORITY SITES, CONSTRUCTION OF VARIOUS WATER SUPPLY PROJECTS, TALIBON,(WATER SYSTEM)

  • Location: Bohol
  • Owner: DPWH – Bohol 2nd District
  • Cost: 30.2M
  • Period: 181 C.D.
  • Status: Completed / June 2017

[UNVERIFIED] Bulk Water Supply at Municipality of Corella, Bohol,(WATER SYSTEM)

  • Location: Bohol
  • Owner: Islander Water Resources, Inc.
  • Cost: 258.1M
  • Period: 247 C.D.
  • Status: Completed / June 2017

Construction / Rehabilitation Of San Francisco Water Supply System (Water System)

  • Location: San Fransisco, So. Leyte
  • Owner: LGU – San Fransisco, So. Leyte
  • Cost: 12.5M
  • Period: 150 C.D.
  • Status: Completed / May 2006

Construction for the Devt. / Rehab. Expansion of Municipal Waterworks System (Water System)

  • Location: Matalom, Leyte
  • Owner: LGU – Matalom, So, Leyte
  • Cost: 18.2M
  • Period: 150 C.D.
  • Status: Completed / June 2006

Construction of Dam Embankment Phase II, Talibon Small Reservoir Irrigation Project (Irrigation)

  • Location: Zamora, Talibon Bohol
  • Owner: National Irrigation Authority
  • Cost: 12.5M
  • Period: 270 C.D.
  • Status: Completed / August 2006

Improvement & Expansion of Existing Malalag Waterworks System (Water System)

  • Location: Malalag, Davao Del Sur
  • Owner: LGU – Municipality of Malalag
  • Cost: 14.5M
  • Period: 300 C.D.
  • Status: Completed / May 2005

Construction of Cagwait Municipal Water System (Water System)

  • Location: Cagwait, Surigao Sur
  • Owner: Municipality of Cagwait Surigao Sur
  • Cost: 23.7M
  • Period: 240 C.D.
  • Status: Completed / June 2004

Construction of Lanuza Municipal Water System (Water System)

  • Location: Lanuza, Surigao Sur
  • Owner: Municipality of Lanuza Surigao Sur
  • Cost: 11.9M
  • Period: 180 C.D.
  • Status: Completed / January 2004

Improvement of Waterworks System for First Congressional District of Bohol (Water System)

  • Location: First District of Bohol
  • Owner: DPWH Bohol 1st Engg District
  • Cost: 20.1M
  • Period: 125 C.D.
  • Status: Completed / June 2002

Construction of Daan Bantayan Water Works (Water System)

  • Location: Daan Bantayan, Cebu
  • Owner: Municipality of Daan Bantayan
  • Cost: 26M
  • Period: 180 C.D.
  • Status: Completed / June 1999

Flood Control

CLUSTER 2- CONSTRUCTION/UPGRADE/REHABILITATION OF SLOPE PROTECTION/ SEAWALL MADRIDEJOS, CEBU: BRGY TARONG & BRGY MAALAT(FLOOD CONTROL)

  • Location: Cebu
  • Owner: DPWH – Cebu 1st District Engineering Office
  • Cost: 26.4M
  • Period: 124 C.D.
  • Status: Completed / October 2017

CLTR 1-CONSTRUCTION/UPGRADE/REHABILITATION OF SLOPE PROTECTION/SEAWALL, MADRIDEJOS, CEBU: BRGY MALBAGO & BRGY MANCILANG (FLOOD CONTROL)

  • Location: Cebu
  • Owner: DPWH – Cebu 1st District Engineering Office
  • Cost: 24.5M
  • Period: 123 C.D.
  • Status: Completed / October 2017

IMP/WIDENING OF FATIMA MALABOG ROAD INCLUDING SLOPE PROTECTION DAVAO CITY,K1504+223- K1504+250,K1501+(FLOOD CONTROL)

  • Location: Davao City
  • Owner: DPWH – Davao City District Engineering Office
  • Cost: 36.1M
  • Period: 164 C.D.
  • Status: Completed / October 2017

CONSTRUCTION OF SEAWALL ALONG COASTAL AREA, POB.MANUKAN TO MANUKAN RIVER (PHASE2) POB. EAST MANUKAN (FLOOD CONTROL)

  • Location: Zamboanga del Norte
  • Owner: DPWH – Zamboanga del Norte 1st District Engineering Office
  • Cost: 40.5M
  • Period: 211 C.D.
  • Status: Completed / August 2012

REPAIR OF OPOL BRIDGE APPROACHES & RECONSTRUCTION OF THE RIVER FLOOD CONTROL REVETMENT ALONG BUTUAN-CDOC-I (Flood Control)

  • Location: Butuan
  • Owner: DPWH – Region X
  • Cost: 24.1M
  • Period: 181 C.D.
  • Status: Completed / September 2010

RESTORATION OF DAMAGED FLOOD CONTROL STRUCTURE, BRGY. 43 CAVIT, LAOAG
CITY (Flood Control)

  • Location: Ilocos Norte
  • Owner: DPWH – Ilocos Norte 1st District Engineering Office
  • Cost: 5.19M
  • Period: 52 C.D.
  • Status: Completed / May 2010

CONSTRUCTION OF FLOOD CONTROL ALONG THE LEFT BANK OF DIPOLOG RIVER CONTROL, LOOC, ESTAKA, DIPOLOG (Flood Control)

  • Location: Dipolog
  • Owner: DPWH – Zamboanga del Norte 1st District Engineering Office
  • Cost: 62.3M
  • Period: 501 C.D.
  • Status: Completed / December 2013

CONSTRUCTION OF SIMUAY FLOOD CONTROL PROJECT (WIDENING OF PILOT CHANNEL) KM. 0+780 TO KM 6+100 (Flood Control)

  • Location: Simuay, Sultan Kudarat
  • Owner: DPWH – Region XII
  • Cost: 59.7M
  • Period: 272 C.D.
  • Status: Completed / September 2013

CONSTRUCTION OF FLOOD CONTROL AT DISAKAN BRIDGE, JOSE DALMAN, ZAMBOANGA DEL NORTE (Flood Control)

  • Location: Zamboanga del Norte
  • Owner: DPWH – Zamboanga del Norte 1st District Engineering Office
  • Cost: 6.5M
  • Period: 156 C.D.
  • Status: Completed / June 2013

CONSTRUCTION OF DRAINAGE/PROTECTION ALONG DIPOLOG SINDANGAN- LILOY ROAD AT
SITIO CURVADA, GALAS, DIPOLOG (Flood Control)

  • Location: Zamboanga del Norte
  • Owner: DPWH – Zamboanga del Norte 1st District Engineering Office
  • Cost: 675K
  • Period: 64 C.D.
  • Status: Completed / June 2013

CONSTRUCTION OF CROSS DRAINAGE ALONG DIPOLOG-OROQUIETA ROAD, MINAOG SECTION, DIPOLOG CITY (Flood Control)

  • Location: Zamboanga del Norte
  • Owner: DPWH – Zamboanga del Norte 1st District Engineering Office
  • Cost: 2.3M
  • Period: 61 C.D.
  • Status: Completed / June 2013

REPAIR/REHABILITATION OF SPILLWAY FOR BINUANGAN RIVER ALONG BAGAC-MARIVELES ROAD, BAGAC, BATAAN (Flood Control)

  • Location: Bataan
  • Owner: DPWH – Bataan 2nd District Engineering Office
  • Cost: 1.8M
  • Period: 39 C.D.
  • Status: Completed / February 2012

CP-4: IMPROVEMENT/CONCLUSION OF KAPALONG-TALAINGOD- VALENCIA, BUKIDNON ROAD, BRGY. STO.NINO SECTION, PHASE I (Flood Control)

  • Location: Bukidnon
  • Owner: DPWH- Region XI
  • Cost: 13.1M
  • Period:  1153 C.D.
  • Status: Completed / August 2011

CP-8 CONSTRUCTION OF SIX(6) BRIDGES INCLUDING ALONG KAPALONG-TALAINGOD-VALENCIA, BUKIDNON RD. (Flood Control)

  • Location: Zamboanga del Norte
  • Owner: DPWH- Region XI
  • Cost: 15M
  • Period:  1020 C.D.
  • Status: Completed / April 2011